top of page
Water Line Installation Project
Project: Installation of 6-inch pipeline in the Right-of-Way
​Location: North Fulshear Drive, from FM 359 to Sprigg Street
Duration: 2 - 4 Weeks
​
Scope of Work - Summary of Plans
Installation of approximately 4,000 linear feet of 6-inch C900 PVC water pipeline along the right of way at a depth of 2 feet. Work includes trench excavation and boring, connection to an existing 16-inch water main using a tapping sleeve, hydrostatic testing, flushing, and site restoration to pre-construction conditions. All work will comply with local regulations and approved standards.
​
Approved by the Fort Bend County Engineering Department
(Project Number: 2025 - 76332)


Note: Tap is from City of Fulshear
Permitted by:
- Fort Bend County Engineering Department
- Fort Bend County Drainage District
- City of Fulshear